Strata Upgrade // Annandale

Complete Window and Door Replacement for Strata Block

Strata projects are always a pleasure to work on.

We provide economies of scale to Strata companies, and provide an exponentially more inexpensive replacement program of works at scale like this. This means it benefits owners from a reduce cost or none at all if covered by the fund, and the strata itself for improvements to the building which really positively impacts everyone within it.

Once we moved past the usual tender process, the scope and design of the windows was simple. We offered some variations to owners where needed and it was taken up individually as long as it did not impact the exterior look of the building. We took care of all communications with tenants and owners, organised times to replace with everyone to reduce impact to their lives as little as possible and from go ahead, to design completion took 6 weeks, with individual windows being fitted over the course of the next 4 weeks.

 

STATS

  • Work
    Replacing all windows and doors
  • Special Fittings/Features
    Security doors, restricted opening windows
  • Timeframe
    Design and approvals 6 weeks, and fitting completed over 4 weeks.